On Wed, 2 Apr 2003 15:37:28 -0800 Dan Lockwood <[email protected]> wrote:
> Our current plan is to purchase the UPS with a minimal amount of
> battery, approximately 15min worth; just enough to get the generator
> running.  Is this the better way to go?  Or should we consider more
> battery? 

just how certain are you that your generator is always going to start
within 15 minutes?

richard
--
Richard Welty                                         [email protected]
Averill Park Networking                                         518-573-7592
              Unix, Linux, IP Network Engineering, Security