North American Network Operators Group Date Prev | Date Next | Date Index | Thread Index | Author Index | Historical Re: San Francisco Power Outage
Speaking on Deep Background, the Press Secretary whispered: > Level 4 datacenters can, and will, fail. Nothing you can > do including just doing 48V DC for everything are truly > foolproof solutions. Hard to find anyone who takes the -48vdc mantra to heart more than an RBOC. Ditto on lightning protection. Yet I recall the Bell South 305-255 CO taking a lightning hit on the incoming power; the 5ESS was down for 3-4 hours. -- A host is a host from coast to [email protected] & no one will talk to a host that's close........[v].(301) 56-LINUX Unless the host (that isn't close).........................pob 1433 is busy, hung or dead....................................20915-1433
|