Vendor S? :)


tv
----- Original Message ----- From: "JC Dill" <[email protected]>
Cc: <[email protected]>
Sent: Tuesday, January 23, 2007 4:11 PM
Subject: Re: Colocation in the US.




Robert Sherrard wrote:

Who's getting more than 10kW per cabinet and metered power from their colo provider?

I had a data center tour on Sunday where they said that the way they provide space is by power requirements. You state your power requirements, they give you enough rack/cabinet space to *properly* house gear that consumers that much power. If your gear is particularly compact then you will end up with more space than strictly necessary.


It's a good way of looking at the problem, since the flipside of power consumption is the cooling problem. Too many servers packed in a small space (rack or cabinet) becomes a big cooling problem.

jc