Re: Chicago NAP status

  • From: Martin Lee Schoffstall
  • Date: Fri Oct 14 07:13:25 1994

does letter of intent mean that you are still awaiting a contract to be real?

while physical connection is interesting

are you aware of any bilateral agreements to make Internet connectivity happen
there?

m

> Chicago NAP Status Report
> 
> Ameritech Advanced Data Services
> 10/14/94
> 
> ISI/Route Server: A letter of intent from ISI has been received. ISI will shi
p
> a cisco 7010 router and Sun workstation to AADS operations in Chicago. The
> equipment space is being prepared, and will be ready by the time the equipmen
t
> arrives.
> 
> MCI: A letter of intent and purchase order from MCI has been received. A DS-3
> circuit to the MCI POP at Downers Grove has been ordered.
> 
> ANS: A letter of intent has been received from ANS. A DS-3 circuit to the ANS
> location at Downers Grove has been ordered.
> 
> Sprint: The order is being worked on. Sprint intends to use their own circuit
> for access to the AADS ATM service.
> 
> We are also in discussions with various other ISP/NSPs and government
> agency networks regarding connection to the NAP.
> 
>         Mark
> 
> 
- - - - - - - - - - - - - - - - -